What deadlines must be paid attention to?

If you have a permit exemption, you must submit a notice of commencement of construction to the lower building supervisory authority at least one week before the start of construction work.
If the construction work is to be started more than three years after the construction work has become permissible in accordance with Section 62 (3) sentences 2 and 3 of the Bremen Building Code, the documents must be submitted to the municipality again.

What are the costs?

The amount of the fee is based on Section 1 of the Cost Ordinance for Construction, Tariff No. 101.08 Notification of the Municipality pursuant to Section 62 (3) Sentence 3 of the Bremen State Building Code and amounts to 1 per cent of the construction costs.