What deadlines must be paid attention to?

You can start your building project with a valid building permit within three years of the preliminary building permit being issued. You can apply for a one-off extension of the preliminary building permit by two years within this period.
The preliminary building permit does not replace a building permit. This must be applied for separately.

How long does it take to process

The lower building supervisory authority should decide on the preliminary building application within twelve weeks after the completeness of the application has been confirmed in accordance with Section 69 (3) of the Bremen State Building Code.

What are the costs?

The amount of the fee is based on Section 1 of the Construction Costs Ordinance, tariff number 101.07 and depends on the number and type of individual questions examined and the scope of the official hearing.