The competent authority must be notified in writing or electronically of any change to the location, type or operation of an installation requiring a permit at least one month before the change is to commence, unless a permit is applied for.

  • You must notify the competent authority of the planned change in writing or, if applicable, using the ELiA web application, available on the website of the Bremen Trade Supervisory Authority.
  • You enclose the necessary documents with the notification, insofar as these may be required to check whether the project requires approval.
  • The competent authority will immediately confirm receipt of the notification and the enclosed documents in writing or electronically
  • in the case of an electronic notification, it may also request additional copies and the transmission of the documents to be enclosed with the notification in written form.
  • Upon receipt of the notification, the competent authority will inform you immediately which additional documents it requires to assess the requirements.
  • If necessary, the competent authority will decide that your project requires a permit. The authority will inform you of its decision within one month
  • You may implement the change as soon as the competent authority informs you that the change does not require approval or the competent authority has not issued a statement one month after the notification documents are complete.
  • In the case of an incident-relevant change, you may only make the change if the competent authority informs you that no approval is required.

Legal bases