What deadlines must be paid attention to?

1 month Objection period after the announcement of the results of the real estate survey against boundary determination and marking.

How long does it take to process

Approx. 3-4 weeks after receipt of the application, the local survey is carried out.
Approximately 7 weeks after receipt of the application, the survey is entered in the real estate register and the cost assessment is sent to the party liable for the costs.

What are the costs?

1.288,50 EUR (gross) at 1 border point
1.735,50 EUR (gross) at two border points
2.182,50 EUR (gross) at three border points
2.629,50 EUR (gross) at 4 border points
Gross costs depending on the number of determined boundary points can be requested from any official surveying office.