Applying for a preliminary decision on an installation requiring approval


What deadlines must be paid attention to?

Period of validity: 2 years (The preliminary decision becomes invalid if you do not apply for approval of the installation within 2 years. In justified exceptional cases, the period of validity of the preliminary decision can be extended for up to 2 further years).

How long does it take to process

Depending on the individual case.

What are the costs?

290 euros to 11,500 euros.
Half of the fee is offset against the respective fee for the permit if the preliminary decision leads to approval without a significant change.