You are here:
  • Dienstleistungen
  • Applying for a permit under hazardous incident law for the construction and operation or modification of an installation that does not require a permit

Applying for a permit under hazardous incident law for the construction and operation or modification of an installation that does not require a permit


Procedure

  • You apply for the modification permit in writing to the competent authority.
  • You enclose the necessary documents with the application.
  • The competent authority confirms receipt of the documents and informs you which additional documents it needs to assess the requirements.
  • The authority involves the public authorities and the public
  • You can only start work on your project once you have received approval.

Legal bases

More information

Approval is not required if you have already ensured the appropriate safety distance in the spatially significant planning or measure by means of binding specifications.

Legal remedy

  • Objection
    • Further information on how to lodge an objection can be found in the decision.
  • Complaint