You are here:

Apply for a building permit for the construction of a plant


What deadlines must be paid attention to?

In accordance with Section 73 (1) of the Bremen Building Code, the building permit and any partial building permit expire if construction of the building project has not commenced within three years of their issue or if construction has been interrupted for more than one year.
The building permit may be extended once for two years in accordance with Section 73 (2) of the Bremen Building Code. Thereafter, a new building application is required in the event of non-utilization.

How long does it take to process

In accordance with Section 69 (3) of the Bremen State Building Code, the lower building supervisory authority shall decide on the building application within twelve weeks after the completeness of the application has been confirmed.

What are the costs?

The amount of the fee is based on § 1 of the Cost Ordinance Construction, tariff number 101.00 and amounts to 9 per cent of the construction costs.